EIC Construction Update

 CT

2013 Review: Can be dedicated to preparing the construction site for a multi-year development. Foundation of the building was poured and work on the steel structure started. Pouring of the foundation and erecting the steel structure were the two most critical milestones for the project. Masha‘Allah,  it showed the commitment from the community to take on this long development effort.

2014 Review: Two significant projects, steel structure and pouring of concrete, were completed. Work started on the next development phase of covering the exposed steel structure. Both these tasks were long, expensive, required significant planning and tested the patience of our community. Alhamdu’lillah, with The Almighty’s blessings and your continued support we persevered.

2015 Review: We started the year with a shell and by the end of the year our Masjid had taken its final shape and looked complete. Masha‘Allah! Majority of the exterior work was completed which included metal work, roofing, stucco, tiles and paint. There was tremendous progress throughout the year. We are grateful to our community who continued their support towards the project.

2016 Review: We made significant progress throughout the year, both on the outside as well as on the inside. This phase of construction required exceptional program management and coordination as there were multiple tasks running in parallel. Insides of the facility started to take shape with walls, ceiling, windows and doors in place. Alhamdu’lillah, with The Almighty’s blessings and tremendous support from the community we made significant step forward towards the goal.

2017 Review: Turned out to be a tremendous year for project as we were able to complete create several critical tasks and secure a temporary permit of occupancy, Alhamdu’lillah! This allowed us to enjoy the blessed month of Ramadan in the new facility, along with performing daily Salah’s. With the additional capacity we were able to pray both Eid prayers at the new facility as well. We were also able to complete the initial phase of parking which added 50 new parking spots within the premises and improved traffic congestion on the nearly streets. 

2018 Progress: Where has the time gone? The blessed month of Ramadan is upon us. Construction work has been progressing at a feverish pitch. Alhamdu’lillah, by the blessings of Allah (swt) we celebrated our annual open house event with the opening of the new parking lot. It was a major project with a tight timeline, we now have the final grading in place and the parking capacity of ~150 vehicles. This will allow our community to park the cars inside the facility and remove congestion from the nearby streets. Our goal before Ramadan is not complete yet as the work in basement continues. We need to wrap it up in next 10 days (May 14th)!

We are grateful to our community who has continued their monitory support over the years. These are arduous and costly tasks which span multiple months. This is active construction area with heavy machines still at the premises so please exercise extreme caution!  These are electrifying times at EIC as we continue to make progress towards our goal and witness the completion of a magnificent Masjid.

We ask our community to continue to pray for expeditious, smooth and safe completion of the work.  We have been collecting pictures of construction over the last few years and felt that it was important to share this journey with our community and supporters.

Click the pictures link to see the latest construction pictures.

Click the video link to watch years of tough work in a span of minutes.

Funds Needed Immediately

 

Click to Donate Now